BHP Kwinana Hydrogen Plant

Overview

​

From March until June 2012 Hender Lee provided the forward works package for the new hydrogen plant at BHP in Kwinana WA. 

​

Scope

​

  • Vertical Drilling for Stainless Steel 

  • Earthing vertical conductor installations 

  • Plant Earthing Grids and Systems

  • Soil Resistivity Enhancement.

  • Specific Earthing Components Manufacture.

  • Detailed System Compliance and Environmental Conditions Testing, Recording and Certification

  • Cable Access, Earthing and Lighting Protection System for the new Hydrogen Plant allocation.

​

Challenges

​

Hender Lee Electrical delivered the workings within the intrinsically safe and hazardous area restrictions.  